Install progress for photovoltaics

We'll have the PV modules on two different roofs. After deciding on the (aesthetically and technically) best route, conduit was installed to carry wiring from the upper level roof to the lower level. Because of our property's peculiar lines of sight, you don't really notice it from the street or backyard. The conduit can be painted later.

Ground wires (for lightning safety) were pulled and connected to rails, and a supplemental 6-foot ground rod driven into the ground.
To carry wiring, there's nice flashing that will be tucked under the panels.
A junction box is also on the roof, where it all connects together on the way to the inverter.

Tomorrow's plan is to get the panels on the rails, and an official inspection.